Chapter 15.12
PERMITTING PROCESS FOR ELECTRIC VEHICLE CHARGING SYSTEMS

Sections:

15.12.010    Purpose.

15.12.020    Expedited permitting process.

15.12.030    Association approval.

15.12.040    Permit application processing.

15.12.050    Technical review.

15.12.060    Inconsistent provisions repealed.

15.12.010 Purpose.

The purpose of this chapter is to promote and encourage the use of electric vehicles by creating an expedited, streamlined permitting process for electric vehicle charging stations while promoting public health and safety and preventing specific adverse impacts in the installation and use of such charging stations. This chapter is also purposed to comply with California Government Code Section 65850.7. (Ord. 1828 §2, 2022).

15.12.020 Expedited permitting process.

Consistent with Government Code Section 65850.7, the building official shall implement an expedited, streamlined permitting process for electric vehicle charging stations, and adopt a checklist of all requirements with which electric vehicle charging stations shall comply in order to be eligible for expedited review. The expedited, streamlined permitting process and checklist may refer to the recommendations contained in the most current version of the "Plug-In Electric Vehicle Infrastructure Permitting Checklist" of the "Zero-Emission Vehicles in California: Community Readiness Guidebook" as published by the Governor’s Office of Planning and Research. The county’s adopted checklist shall be published on the county’s website. (Ord. 1828 §2, 2022).

15.12.030 Association approval.

Consistent with Government Code Section 65850.7, the building official shall not condition the approval for any electric vehicle charging station permit on the approval of such a system by an association, as that term is defined by Civil Code Section 4080. (Ord. 1828 §2, 2022).

15.12.040 Permit application processing.

A permit application that satisfies the information requirements in the county’s adopted checklist shall be deemed complete and be promptly processed. Upon confirmation by the building official that the permit application and supporting documents meet the requirements of the county’s adopted checklist, and are consistent with all applicable laws, the building official shall, consistent with Government Code Section 65850.7, approve the application and issue all necessary permits. Such approval does not authorize an applicant to energize or utilize the electric vehicle charging station until approval is granted by the county. If the building official determines that the permit application is incomplete, he or she shall issue a written correction notice to the applicant, detailing all deficiencies in the application and any additional information required to be eligible for expedited permit issuance. (Ord. 1828 §2, 2022).

15.12.050 Technical review.

It is the intent of this chapter to encourage the installation of electric vehicle charging stations by removing obstacles to permitting for charging stations so long as the action does not supersede the building official’s authority to address higher priority life-safety situations. If the building official makes a finding based on substantial evidence that the electric vehicle charging station could have a specific adverse impact upon the public health or safety, as defined in Government Code Section 65850.7, the county may require the applicant to apply for a use permit. (Ord. 1828 §2, 2022).

15.12.060 Inconsistent provisions repealed.

Any provision of the Amador County Municipal Code or appendices thereto, inconsistent with the provisions of this chapter, to the extent of such inconsistencies and no further, are hereby repealed or modified to that extent necessary to effect the provisions of this chapter. (Ord. 1828 §2, 2022).