40.610.040 Imposition of Impact Fee
A. No building permit shall be issued for applicable development in a designated service area as defined in this chapter unless the impact fee is calculated and imposed pursuant to this chapter.
(Amended: Ord. 2018-10-02)
B. Impact fees shall be calculated at the time of building permit issuance.
(Amended: Ord. 2005-04-12; Ord. 2018-10-02)
C. For applicable development not necessitating or having been previously granted preliminary plat, preliminary short plat or site plan approval, the impact fee shall be calculated and imposed at the time of building permit application.
(Amended: Ord. 2018-10-02)
D. For applicable development not necessitating a building permit, the impact fee shall be calculated and imposed at the time of site plan approval.
(Amended: Ord. 2018-10-02)
E. For manufactured home parks, the impact fee shall be calculated and imposed at the time of site plan approval.
(Amended: Ord. 2016-06-12; Ord. 2018-10-02)