Division 8. Building Permits, Variances and Conditional Uses
Chapter 17.125
BUILDING PERMITS
Sections:
17.125.010 Purpose and intent.
17.125.020 Application procedure.
17.125.030 Building official review.
17.125.010 Purpose and intent.
The purpose of this chapter is to insure that no building or structure shall be erected, moved, added to or structurally altered without a permit issued by the building official of the town of Coulee Dam. (Ord. 536 § 1 (§ 27.01), 2000)
17.125.020 Application procedure.
All applications for building permits are subject to review under Division 10. (Ord. 536 § 1 (§ 27.02), 2000)
17.125.030 Building official review.
The building official shall review the application for compliance with the provisions of this title and any other applicable codes or ordinances. If the building official finds that the proposed structure is not in compliance with applicable ordinances and codes, the building official shall deny the application and return the application to the applicant with a written explanation of the reasons for denying the application.
The applicant may resubmit the application; provided, that the structure is modified to meet the requirements of all codes and ordinances. Upon receipt of a building permit, substantial construction of the structure must start within six months of the issuance of the permit. If substantial construction has not started within six months, the applicant must submit a request for extension of the permit. (Ord. 536 § 1 (§ 27.03), 2000)