Chapter 14.55
AFFIRMATIVE DEFENSES TO DISCHARGE VIOLATIONS

Sections:

14.55.010    Upset.

14.55.020    Prohibited discharge standards.

14.55.030    Bypass.

14.55.010 Upset.

A. Users shall control production of all discharges to the extent necessary to maintain compliance with applicable pretreatment standards upon reduction, loss, or failure of its treatment facility until the facility is restored or an alternative method of treatment is provided. This requirement applies in the situation where, among other things, the primary source of power of the treatment facility is reduced, lost, or fails.

B. For the purposes of this chapter, an upset does not include noncompliance to the extent caused by operational error, improperly designed treatment facilities, inadequate treatment facilities, lack of preventive maintenance, or careless or improper operation.

C. An upset shall constitute an affirmative defense to an action brought for noncompliance with applicable pretreatment standards if the requirements of subsection D of this section are met.

D. A user who wishes to establish the affirmative defense of upset to an enforcement action brought for noncompliance with applicable pretreatment standards shall demonstrate, through properly signed, contemporaneous operating logs, or other relevant evidence that:

1. An upset occurred and the user can identify the cause(s) of the upset; and it was not due to improperly designed or inadequate treatment facilities, lack of preventive maintenance, or careless or improper operation;

2. The facility was at the time being operated in a prudent and workman-like manner and in compliance with applicable operation and maintenance procedures; and

3. The user has submitted the following information to the City, the POTW and treatment plant operator within 24 hours of becoming aware of the upset (if this information is provided orally, a written submission must be provided within five days):

a. A description of the indirect discharge and cause of noncompliance;

b. The period of noncompliance, including exact dates and times or, if not corrected, the anticipated time the noncompliance is expected to continue; and

c. Steps being taken and/or planned to reduce, eliminate, and prevent recurrence of the noncompliance.

E. In any enforcement proceeding, the user seeking to establish the occurrence of an upset shall have the burden of proof.

F. Users will have the opportunity for a judicial determination on any claim of upset only in an enforcement action brought for noncompliance with applicable pretreatment standards. (Ord. 2381 § 11, 2005).

14.55.020 Prohibited discharge standards.

A user shall have an affirmative defense to an enforcement action brought against it for noncompliance with the prohibitions in MTMC 14.10.010(A) and (B)(3) through (7) if it can prove that it did not know, or have reason to know, that its discharge, alone or in conjunction with discharges from other sources, would cause pass through or interference and that either: (A) a local limit exists for each pollutant discharged and the user was in compliance with each limit directly prior to, and during, the pass through or interference; or (B) no local limit exists, but the discharge did not change substantially in nature or constituents from the user’s prior discharge when the city of Edmonds was regularly in compliance with its NPDES permit, and in the case of interference, was in compliance with applicable sludge use or disposal requirements. (Ord. 2381 § 11, 2005).

14.55.030 Bypass.

A. For the purposes of this chapter, “severe property damage” means substantial physical damage to property, damage to the treatment facilities which causes them to become inoperable, or substantial and permanent loss of natural resources which can reasonably be expected to occur in the absence of a bypass. “Severe property damage” does not mean economic loss caused by delays in production.

B. A user may allow any bypass to occur which does not cause applicable pretreatment standards or requirements to be violated, but only if it also is for essential maintenance to assure efficient operation. Such bypasses are not subject to subsections C and D of this section.

C. 1. If a user knows in advance of the need for a bypass, it shall submit prior notice to the City and the POTW, at least 10 days before the date of the bypass, if possible.

2. User shall submit oral notice to the City and to the POTW of an unanticipated bypass that exceeds applicable pretreatment standards within 24 hours from the time it becomes aware of the bypass. A written submission shall also be provided within five days of the time the user becomes aware of the bypass. The written submission shall contain a description of the bypass and its cause; the duration of the bypass, including exact dates and times, and, if the bypass has not been corrected, the anticipated time it is expected to continue; and steps taken or planned to reduce, eliminate, and prevent reoccurrence of the bypass. The City with concurrence of the POTW may waive the written report on a case-by-case basis if the oral report has been received within 24 hours.

D. 1. Bypass is prohibited, and the City and/or POTW may take an enforcement action against a user for a bypass, unless:

a. Bypass was unavoidable to prevent loss of life, personal injury, or severe property damage;

b. There were no feasible alternatives to the bypass, such as the use of auxiliary treatment facilities, retention of untreated wastes, or maintenance during normal periods of equipment downtime. This condition is not satisfied if adequate back-up equipment should have been installed in the exercise of reasonable engineering judgment to prevent a bypass which occurred during normal periods of equipment downtime or preventive maintenance; and

c. The user submitted notices as required under subsection C of this section.

2. The City with concurrence of the POTW may approve an anticipated bypass, after considering its adverse effects, if the POTW determines that it will meet the three conditions listed in subsection (D)(1) of this section. (Ord. 2381 § 11, 2005).