Chapter 19.08
PUBLIC WORKS CONSTRUCTION SPECIFICATIONS

Sections:

19.08.010    Adoption by reference.

19.08.020    Uniform code – Copy.

19.08.030    Variance from specifications permitted.

19.08.040    Preconstruction meeting.

19.08.050    Testing and inspection.

19.08.010 Adoption by reference.

The Town of Wilkeson adopts the Standard Specifications for Road, Bridge and Municipal Construction, and the Standard Plans for Road, Bridge and Municipal Construction prepared by the Washington Department of Transportation and the Washington State Chapter, American Public Works Association (1997 Edition as may be amended or supplemented), for all public works constructed inside the Town, and for all works which are to be dedicated to the Town of Wilkeson or utilized by the Town of Wilkeson or its citizens for public purposes, with modifications to said standard specifications as herein specifically set out in this chapter. [UDC Ord. dated 7/21/1998].

19.08.020 Uniform code – Copy.

A copy of said standard specifications and special Town of Wilkeson requirements shall be kept on file at the Town Hall by the Town Engineer. [UDC Ord. dated 7/21/1998].

19.08.030 Variance from specifications permitted.

The Town Council of the Town of Wilkeson may approve varying from the standards of the Standard Specifications for Municipal Public Works Construction by resolution or motion. Standards at variance with said standard specifications may also be incorporated into written contracts entered into by the Town and approved by the Town Engineer, or may be incorporated into binding site plans, plats, or other written plans, so long as approved by the Town Engineer. [UDC Ord. dated 7/21/1998].

19.08.040 Preconstruction meeting.

Prior to the construction of public works, or works to become public by dedication or usage, all interested parties including developers, engineers, contractors, and property owners shall meet with the Town Engineer and Public Works Director for the purpose of reviewing all the requirements of said standard specifications and answering any questions relative to the particular project. [UDC Ord. dated 7/21/1998].

19.08.050 Testing and inspection.

Town approved or supervised testing inspection of all utilities may be conducted as phases are completed, at the expense of the contractor; however, this does not constitute final acceptance by the Town.

The contractor shall, if required by the Town, at his own expense, do overall testing of all utilities after the completion of all work. [UDC Ord. dated 7/21/1998].