Division 13-06-003
Grading Plans

Sections:

13-06-003-0001    Plan and Support Information Required

13-06-003-0002    Plan Presentation

13-06-003-0001 Plan and Support Information Required

A.    Approval of these plans by the City is for a one (1) year period, subsequent to the date of approval. If construction work is not started within the one (1) year period, or has been discontinued for any reason for longer than one year, the plans shall be resubmitted for review and re-approval.

B.    Grading plans shall meet all requirements of Appendix J of the currently adopted International Building Codes and the City of Flagstaff Stormwater Management Design Manual. Supporting soils analysis and hydrologic studies may be required. Any excavation or fill exceeding fifty (50) cubic yards will require a grading plan and grading permit. When a soils report is required, it shall be referenced on the grading plans by firm, project number, and date.

C.    To ensure coordination between grading and landscaping plans, the following note shall appear on all grading plans:

By signing these plans, the designer of the landscaping plans confirms that these grading plans have been reviewed, is aware of the scope of the project, and has identified and addressed any potential conflicts between the grading and landscaping plans.

_____________________________

______________

Landscape Designer

Date

D.    To ensure coordination between grading and landscaping plans, the following note shall appear on all landscaping plans:

By signing these plans, the designer of the grading plans confirms that these landscaping plans have been reviewed, is aware of the scope of the project, and has identified and addressed any potential conflicts between the grading and landscaping plans.

_____________________________

______________

Engineer/Designer

Date

(Ord. 2017-22, Rep&ReEn, 07/05/2017)

13-06-003-0002 Plan Presentation

One (1) mylar (four (4) mil. double matte) of the approved grading and drainage plan(s) shall be submitted as public record prior to issuance of the grading permit.

At a minimum, the grading plan shall be prepared in accordance with the City of Flagstaff Stormwater Design Manual and the latest edition of the International Building Code. (Ord. 2017-22, Rep&ReEn, 07/05/2017)