Chapter 13.10
ELECTRIC VEHICLE CHARGING STATION PERMIT EXPEDITING

Sections:

13.10.010    Title, words and phrases.

13.10.020    Expedited review process.

13.10.030    Association approval.

13.10.040    Permit application processing.

13.10.050    Technical review.

13.10.010 Title, words and phrases.

This chapter shall be known as the city of Aliso Viejo electric vehicle charging station permit expediting ordinance. The terms, phrases, and words used in this chapter shall be construed in compliance with the definitions set forth by California Government Code Section 65850.7. [Ord. 2017-191 § 1].

13.10.020 Expedited review process.

Consistent with California Government Code Section 65850.7, the building official shall implement an expedited administrative permit review process for electric vehicle charging stations, and adopt a checklist of all requirements with which electric vehicle charging stations shall comply with in order to be eligible for expedited review. The expedited administrative permit review process and checklist may refer to the recommendations in the checklist prescribed by the most current version of the “Plug-In Electric Vehicle Infrastructure Permitting Checklist” of the “Zero-Emission Vehicles in California: Community Readiness Guidebook” published by the Governor’s Office of Planning and Research. The city’s adopted checklist shall be published on the city’s website. [Ord. 2017-191 § 3].

13.10.030 Association approval.

Consistent with California Government Code Section 65850.7, the building official shall not condition the approval for any electric vehicle charging station permit on the approval of such a system by an association, as that term is defined by California Civil Code Section 4080. [Ord. 2017-191 § 4].

13.10.040 Permit application processing.

A permit application that satisfies the information requirements in the city’s adopted checklist shall be deemed complete and be promptly processed. Upon confirmation by the building official that the permit application and supporting documents meet the requirements of the city’s adopted checklist, and are consistent with all applicable laws, the building official shall, consistent with California Government Code Section 65850.7, approve the application and issue all necessary permits. Such approval does not authorize an applicant to energize or utilize the electric vehicle charging station until approval is granted by the city. If the building official determines that the permit application is incomplete, he or she shall issue a written correction notice to the applicant, detailing all deficiencies in the application and any additional information required to be eligible for expedited permit issuance. [Ord. 2017-191 § 5].

13.10.050 Technical review.

It is the intent of this chapter to encourage the installation of electric vehicle charging stations by removing obstacles to permitting for charging stations so long as the action does not supersede the building official’s authority to address higher priority life-safety situations. If the building official makes a finding based on substantial evidence that the electric vehicle charging station could have a specific adverse impact upon the public health or safety, as defined in California Government Code Section 65850.7, the city may require the applicant to apply for a use permit. [Ord. 2017-191 § 6].