Chapter 12.20
UNDERGROUND UTILITY DISTRICT

Sections:

12.20.010    Definitions.

12.20.020    Public hearing to ascertain necessity – Owner notification of hearing – Decision final.

12.20.030    District designation by resolution – Resolution requirements.

12.20.040    Compliance with order of Council required – Exception.

12.20.050    Conditions for temporary installation of overhead facilities.

12.20.060    Types of facilities exempt.

12.20.070    Notification procedure to property owners and utility companies.

12.20.080    Responsibility of utility company.

12.20.090    Responsibility of property owners – City’s right to disconnect.

12.20.100    Responsibility of City.

12.20.110    Extension of time.

12.20.010 Definitions.

Whenever in this chapter the words or phrases defined in this section are used, they shall have the respective meanings assigned to them in the following definitions:

A. “Commission” shall mean the Public Utilities Commission of the State.

B. “Poles, overhead wires and associated overhead structure” shall mean poles, towers, supports, wires, conductors, guys, stubs, platforms, cross-arms, braces, transformers, insulators, cutouts, switches, communication circuits, appliances, attachments and appurtenances located above ground within a district and used or useful in supplying electric, communication or similar or associated service.

C. “Underground utility district” or “district” shall mean that area in the City within which poles, overhead wires, and associated overhead structures are prohibited as such area is described in a resolution adopted pursuant to the provisions of CMC 12.20.030.

D. “Utility” includes all persons supplying electric, communication or similar or associates service by means of electrical materials or devices. (Ord. 298 § 2, 1973; Ord. 264 § 1, 1967).

12.20.020 Public hearing to ascertain necessity – Owner notification of hearing – Decision final.

A. The Council may from time to time call public hearings to ascertain whether the public necessity, health, safety or welfare requires the removal of poles, overhead wires and associated overhead structures within designated areas of the City and the underground installation of wires and facilities for supplying electric, communication, or similar or associated service.

B. The City Clerk shall notify all affected property owners as shown on the last equalized assessment roll and utilities concerned by mail of the time and place of such hearings at least 10 days prior to the date thereof.

C. Each such hearing shall be open to the public and may be continued from time to time.

D. At each such hearing all persons interested shall be given an opportunity to be heard.

E. The decision of the Council shall be final and conclusive. (Ord. 298 § 2, 1973; Ord. 264 § 1, 1967).

12.20.030 District designation by resolution – Resolution requirements.

A. If after any such public hearing the Council finds that the public necessity, health, safety or welfare requires such removal and such underground installation within a designated area, the Council shall, by resolution, declare such designated area an underground utility district and order such removal and underground installation.

B. Such resolution shall include a description of the area comprising such district and shall fix the time within which such removal and underground installation shall be accomplished and within which affected property owners must be ready to receive underground service.

C. A reasonable time shall be allowed for such removal and underground installation, having due regard for the availability of labor, materials and equipment necessary for such removal and for the installation of such underground facilities as may be occasioned thereby. (Ord. 298 § 2, 1973; Ord. 264 § 1, 1967).

12.20.040 Compliance with order of Council required – Exception.

Whenever the Council creates an underground utility district and orders the removal of poles, overhead wires and associated overhead structures therein as provided in CMC 12.20.030, it is unlawful for any person or utility to erect, construct, place, keep, maintain, continue, employ or operate poles, overhead wires and associated overhead structures in the district after the date when said overhead facilities are required to be removed by such resolution. However, such overhead structures may be kept as required to furnish service to an owner or occupant of property prior to the performance by such owner or occupant of the underground work necessary for such owner or occupant to continue to receive utility service and for such reasonable time as is required to remove said facilities after the underground work has been performed. (Ord. 298 § 2, 1973; Ord. 264 § 1, 1967).

12.20.050 Conditions for temporary installation of overhead facilities.

A. Notwithstanding the provisions of this chapter, overhead facilities may be installed and maintained for a period, not to exceed 10 days, without authority of the Council in order to provide emergency service.

B. The Council may grant special permission, on such terms as the Council may deem appropriate, in cases of unusual circumstances, without discrimination as to any person to erect, construct, install, maintain, use or operate poles, overhead wires and associated overhead structures. (Ord. 298 § 2, 1973; Ord. 264 § 1, 1967).

12.20.060 Types of facilities exempt.

This chapter and any resolution adopted pursuant to CMC 12.20.030 shall, unless otherwise provided in such resolution, not apply to the following types of facilities:

A. Any municipal facilities or equipment installed under the supervision and to the satisfaction of the City Engineer;

B. Poles or electroliers used exclusively for street lighting;

C. Overhead wires, exclusive of supporting structures, crossing any portion of a district within which overhead wires have been prohibited, or connecting to buildings on the perimeter of a district, when such wires originate in an area from which poles, overhead wires and associated overhead structures are not prohibited;

D. Poles, overhead wires and associated overhead structures used for the transmission of electric energy at nominal voltages in excess of 34,500 volts;

E. Overhead wires attached to the exterior surface of a building by means of a bracket or other fixture and extending from one location on the building to another location on the same building or to an adjacent building without crossing any public street;

F. Antennas, associated equipment and supporting structures, used by a utility for furnishing communication services;

G. Equipment appurtenant to underground facilities, such as surface mounted transformers, pedestal mounted terminal boxes and meter cabinets, and concealed ducts;

H. Temporary poles, overhead wires and associated overhead structures used or to be used in conjunction with construction projects. (Ord. 298 § 2, 1973; Ord. 264 § 1, 1967).

12.20.070 Notification procedure to property owners and utility companies.

A. Within 10 days after the effective date of a resolution adopted pursuant to CMC 12.20.030, the City Clerk shall notify all affected utilities and all persons owning real property within the district created by said resolution.

B. The City Clerk shall further notify such affected property owners of the necessity that, if they or any person occupying such property desire to continue to receive electric, communication, or similar or associated service, they or such occupant shall provide all necessary facility changes on their premises so as to receive such service from the lines of the supplying utility or utilities at a new location, subject to applicable rules, regulations and tariffs of the respective utility or utilities on file with the commission.

C. Notification by the City Clerk shall be made by mailing a copy of the resolution adopted pursuant to CMC 12.20.030, together with a copy of the ordinance codified in this chapter, to affected property owners as such are shown on the last equalized assessment roll and to the affected utilities. (Ord. 298 § 2, 1973; Ord. 264 § 1, 1967).

12.20.080 Responsibility of utility company.

If underground construction is necessary to provide utility service within a district created by any resolution adopted pursuant to CMC 12.20.030, the supplying utility shall furnish that portion of the conduits, conductors and associated equipment required to be furnished by it under applicable rules, regulations and tariffs on file with the commission. (Ord. 298 § 2, 1973; Ord. 264 § 1, 1967).

12.20.090 Responsibility of property owners – City’s right to disconnect.

A. Every person owning, operating, leasing, occupying or renting a building or structure within a district shall perform construction and provide that portion of the service connection on that person’s property between the facilities referred to in CMC 12.20.040 and the termination facility on or within said building or structure being served, all in accordance with applicable rules, regulations and tariffs of the respective utility or utilities on file with the commission.

B. In the event any person owing, operating, leasing, occupying or renting said property does not comply with the provisions of subsection (A) of this section within the time provided for in the resolution enacted pursuant to CMC 12.20.030, the City Engineer shall post written notice on the property being served and 30 days thereafter shall have the authority to order the disconnection and removal of any and all overhead service wires and associated facilities supplying utility service to said property. (Ord. 298 § 2, 1973; Ord. 264 § 1, 1967).

12.20.100 Responsibility of City.

The City shall remove at its own expense all City-owned equipment from all poles required to be removed under this chapter in ample time to enable the owner or user of such poles to remove the same within the time specified in the resolution enacted pursuant to CMC 12.20.030. (Ord. 298 § 2, 1973; Ord. 264 § 1, 1967).

12.20.110 Extension of time.

In the event that any act required by this chapter or by a resolution adopted pursuant to CMC 12.20.030 cannot be performed within the time provided on account of shortage of materials, war, restraint by public authorities, strikes, labor disturbances, civil disobedience, or any other circumstances beyond the control of the actor, then the time within which such act will be accomplished shall be extended for a period equivalent to the time of such limitation. (Ord. 298 § 2, 1973; Ord. 264 § 1, 1967).