Chapter 3.15
PUBLIC WORKS PROJECTS – PROCEDURES FOR THE SELECTION OF PROFESSIONAL CONSULTING SERVICES

Sections:

Article I. Public Works Projects and Contractors

3.15.010    Definitions.

3.15.020    Public works projects.

3.15.030    Contracts for engineering, architectural, or accounting services – Applicability of restrictions of general statutes.

Article II. Procedures for the Selection of Professional Consulting Services

3.15.040    Additional definitions.

3.15.050    Notice of requirement of professional services.

3.15.060    Basis for contracts – Compensation.

3.15.070    Requirement to comply with state law.

3.15.080    Special procedures for selection of professional services consulting contracts involving federal participation.

3.15.090    Particular procedures involving public works that cost at least $150,000 – Added rules for projects less than or at least $25,000,000.

3.15.100    Additional provisions regarding responsible and responsive bidders.

3.15.110    Incomplete submissions by bidders and subcontractors.

3.15.120    Multiple low bids.

3.15.130    Certified payroll.

3.15.140    Records and documents submitted to be public records.

3.15.150    Materiality.

3.15.160    Bond or certified check – Filing by bidders.

3.15.170    Procedure for accepting quotes.

3.15.180    Alternative procedure for projects costing less than $150,000.

3.15.190    Alternative procedure for projects costing less than $50,000.

3.15.200    Contracts – Notice to proceed – Failure to award and execute contract and to issue notice – Election by bidder to reject contract.

3.15.210    Public buildings – Approval of plans and specifications by licensed architect or engineer.

3.15.220    Road or street work – Open price provisions – Price adjustments of materials – Limitations.

3.15.230    Emergencies – Contracts by invitation.

3.15.240    Plans and specifications – Approval by various agencies.

3.15.250    Completion of project – Procedure.

3.15.260    Final payment – Claims by subcontractors, laborers, or suppliers.

3.15.270    Contract provision for payment of subcontractors, laborers, or suppliers.

3.15.280    Contractor’s payment bond for public works projects in excess of $200,000.

3.15.290    Contracts in excess of $200,000 – Escrow and retainage – Performance bonds.

3.15.300    Wage scale and antidiscrimination provisions.

3.15.310    Necessity of compliance with public works law.

3.15.320    Road or street work contracts – Timely payment of claims – Final payment – Interest for late payment.

3.15.330    Change or alterations of specifications – Change orders.

3.15.340    Dividing cost of a single public work project into two or more projects prohibited.

3.15.350    Trench safety systems.

3.15.360    Plumbing installations – Proof of licensure.

3.15.370    Severability.

Article I. Public Works Projects and Contractors

3.15.010 Definitions.

(A) The definitions set forth in IC 36-1-12-1.2 shall apply throughout this chapter.

(B) Public Work Defined. As used in this chapter, “public work” means the construction, reconstruction, alteration, or renovation of a public building, airport facility, or other structure that is paid for out of a public fund or out of a special assessment. The term includes the construction, alteration, or repair of a highway, street, alley, bridge, sewer, drain, or other improvement that is paid for out of a public fund or out of a special assessment. The term also includes any public work leased by a political subdivision under a lease containing an option to purchase. [Ord. 1446 § 2, 2010. Code 2000 § 177.01].

3.15.020 Public works projects.

(A) The board may purchase or lease materials in the manner provided in IC 5-22 and perform any public work, by means of its own workforce, without awarding a contract whenever the cost of that public work project is estimated to be less than $150,000. Before a board may perform any work under this section by means of its own workforce, the political subdivision or agency must have a group of employees on its staff who are capable of performing the construction, maintenance, and repair applicable to that work. For purposes of this subsection, the cost of a public work project includes the actual cost of materials, labor, equipment, rental, a reasonable rate for use of trucks and heavy equipment owned, and all other expenses incidental to the performance of the project.

(B) The municipal workforce may perform a public work described in subsection (A) of this section only if (1) the workforce, through demonstrated skills, training, or expertise, is capable of performing the public work; and (2) for a public work project under subsection (A) of this section whose cost is estimated to be more than $100,000, the board:

(1) Publishes a notice under IC 5-3-1 that describes the public work that the board intends to perform with its own workforce; and sets forth the projected cost of each component of the public work as described in subsection (A) of this section; and

(2) Determines at a public meeting that it is in the public interest to perform the public work with the board’s own workforce.

(C) A public work project performed by a board’s own workforce must be inspected and accepted as complete in the same manner as a public work project performed under a contract awarded after receiving bid.

(D) When the project involves the rental of equipment with an operator furnished by the owner, or the installation or application of materials by the supplier of the materials, the project is considered to be a public work project and subject to this chapter. However, an annual contract may be awarded for equipment rental and materials to be installed or applied during a calendar or fiscal year if the proposed project or projects are described in the bid specifications. (Confer with IC 36-1-12-3) [Ord. 1517 § 1, 2012. Code 2000 § 177.02].

3.15.030 Contracts for engineering, architectural, or accounting services – Applicability of restrictions of general statutes.

When any public work is proposed to be performed and the board determines by a two-thirds vote that it is expedient and in the best public interest to employ professional engineering, architectural, or accounting services for the planning and financing of the public work and the preparation of plans and specifications, then the limitations and restrictions in the general statutes with respect to invalidity of contracts without an appropriation therefor, payment of fees solely from the proceeds of bonds or assessments when and if issued, and payment of fees solely from a special fund or funds to be provided in the future, do not apply to contracts for those professional services to the extent that such limitations and restrictions might otherwise prevent the payment of fees for services actually rendered in connection with those contracts or affect the obligation to pay those fees. (Confer with IC 36-1-12-3.5) [Ord. 1446 § 2, 2010. Code 2000 § 177.03].

Article II. Procedures for the Selection of Professional Consulting Services

3.15.040 Additional definitions.

For the purpose of this article, in addition to the definitions set forth in HMC 3.15.010, the following definitions shall apply, unless the context clearly indicates or requires a different meaning:

“Consultant” means an individual, partnership, limited liability company, corporation, association, joint venture, firm or any other form of unincorporated enterprise which performs professional services.

“Firm” means an individual, partnership, limited liability company, corporation, association, joint venture, or any other form of unincorporated enterprise.

“Professional services” means services that are:

(A) Within the scope of practices specified by IC 25-4 for architecture, IC 25-31 for professional engineering, or IC 25-21.5 for land surveying; or

(B) Performed by any licensed architect, professional engineer, or land surveyor in connection with his professional employment or practice.

“Public agency” includes a:

(A) Political subdivision of the town, as defined in IC 36-1-2-13;

(B) Municipally owned utility;

(C) Lessor corporation constructing a public facility to be leased to a political subdivision;

(D) Any of the above acting as a local participating agency (LPA) in connection with a public works contract involving federal participation.

“Public works” means the construction, reconstruction, alteration, or renovation of a public building, airport facility, or other structure that is paid for out of a public fund or out of a special assessment. The term includes the construction, alteration, or repair of a highway, street, alley, bridge, sewer, drain, or other improvement that is paid for out of a public fund or out of a special assessment. The term also includes any public work leased by a political subdivision under a lease containing an option to purchase. [Ord. 1145 § 1, 2000; Ord. 1446 § 2, 2010. Code 2000 § 177.04].

    Statutory reference: Procurement of services of architects, engineers and land surveyors, see IC 5-16-11.1; public work, see IC 36-1-12-2.

3.15.050 Notice of requirement of professional services.

(A) When professional services are required for a project, a public agency may:

(1) Publish notice in accordance with IC 5-3-1;

(2) Provide for notice (other than notice in accordance with IC 5-3-1) as it determines is reasonably calculated to inform those performing professional services of a proposed project;

(3) Provide for notice in accordance with both subsections (A)(1) and (2) of this section; or

(4) Determine not to provide any notice.

(B) If the public agency provides for notice under subsection (A)(1), (2), or (3) of this section, each notice must include:

(1) The location of the project;

(2) A general description of the project;

(3) The general criteria to be used in selecting professional services firms for the project file;

(4) The place where any additional project description or specifications are on file;

(5) The hours of business of the public agency; and

(6) The last date for accepting statements of qualifications from interested parties. [Ord. 1145 § 1, 2000; Ord. 1446 § 2, 2010. Code 2000 § 177.05].

3.15.060 Basis for contracts – Compensation.

A public agency may make all contracts for professional services on the basis of competence and qualifications for the type of services to be performed, and negotiate compensation that the public agency determines to be reasonable. [Ord. 1145 § 1, 2000; Ord. 1446 § 2, 2010. Code 2000 § 177.06].

3.15.070 Requirement to comply with state law.

All consultants in public works projects will comply with the provisions of IC 5-16-11 et seq., regarding certain disclosures against conflicts of interest. [Ord. 1145 § 1, 2000; Ord. 1446 § 2, 2010. Code 2000 § 177.07].

3.15.080 Special procedures for selection of professional services consulting contracts involving federal participation.

(A) Applicability. In addition to the foregoing, this section shall apply for the retaining of professional services on contracts involving federal participation so that selection procedures are compatible with appropriate regulations and guidelines of the U.S. Department of Transportation.

(1) Public agencies shall comply with the applicable provisions of this article for all public works projects involving participation by the United States Department of Transportation;

(2) Public agencies may comply with the applicable provisions of this article for all other public works projects.

(B) Necessity for Use of Professional Services (Consultant). Professional services may be requested for a project where:

(1) The in-house capabilities of the public agency are insufficient to accomplish the project within the desirable time; or

(2) The complexity or nature of the project requires specialized expertise; or

(3) It is more economical to engage such services; or

(4) It is otherwise in the public interest.

(C) Authorization for Employment of Consultant. When determined at regular meeting of the public agency that professional consulting services are to be used, the minutes shall show that the public agency has decided to use the services of a consultant.

(D) Record of Consultants. The public agency will develop and keep records according to the following:

(1) The public agency will maintain files and records of consultants who have expressed interest in providing professional services and who have submitted information as to the qualifications of their firm;

(2) The record of consultants will be based upon information provided by each consultant in a manner which may be prescribed, supplemented with such other information as is considered necessary to provide current data about the firm. The information shall include the name, address, list of principals, list of professional/technical/supportive staff, the qualifications and experience of individuals, the history and experience of the firm, the extent of involvement in noteworthy projects and technical and financial references. From time to time, supplemental information may be submitted by the consultant to keep their file current;

(3) The record of listing of consultants will include the firms previously and currently satisfactorily employed by the municipality, and all MBE (minority business enterprises) firms currently listed in a directory on file with the Indiana Department of Administration Minority Business Development Division. The tabulation should produce a listing of four to eight firms for each type of work.

(E) Selection of Consultants. The selection of consultants for specific projects will be made by a majority vote of the relevant governing body of the public entity.

(F) Requests for Proposals. Prior to the consultant selection, the public agency will do the following:

(1) The public agency will prepare a notice of projects for which consultant proposals are being requested that will include the scope of the work that reflects a clear, accurate and detailed description of the technical requirements for the services to be rendered. A list identifying the evaluation factors and their relative importance must be included. The listing is to be posted for 30 days in the office of the public agency;

(2) The notices will be sent to all firms that have met the requirements outlined in subsection (D) of this section, and which have requested in writing that notices covering specific types of projects be sent to them with the firm’s request being renewed annually;

(3) The public agency or the Indiana Department of Transportation will provide a cost estimate before negotiations of fees for the proposed work, considering like projects, risk and complexity, except for contracts awarded under small purchase procedures. This is to be used during negotiations.

(G) Submission of Proposals. Any consultant having information of the firm’s qualification on file in the public agency’s office or submitting it with a proposal may submit proposal(s) for items noted in the notice of request for proposals during the period of time specified in the notice. The proposal must include:

(1) Description of the proposed project;

(2) Description of the anticipated work elements;

(3) Proposed staffing for the work, including designation of project manager;

(4) Proposed schedule of work; and

(5) Information concerning current overhead rate as prepared by a CPA or a registered accountant, or as approved by the Indiana Department of Transportation.

(H) Selection of Consultant. The public agency, after a review of the proposals received for a project, will decide which firm, in its opinion, is found to be most suitable for employment for that project. In keeping with the intent of Indiana’s affirmative action plan and federal regulations concerning employment of MBE firms, the greatest possible consideration for use of these firms will be given during the selection process.

(I) Reasons for Selection. The minutes of the meeting of the public agency will note the reasons for the selection of the recommended consultant.

(J) Further Technical Review. Upon the public agency’s approval, the proposal received from the selected consultant, together with any necessary added information of breakdown of scope, schedule and proposed compensation, with man-hour estimates, overhead rate, direct costs, and the like, will undergo a further technical review by the public agency. As required, preliminary discussions between the consultant and the public agency will take place during these assessments.

(K) When Preaward Audit Is Required. In those instances where 23 CFR 172.5(a)(1) requires preaward audit evaluation on selected consultants which are expected to exceed $250,000, or insufficient knowledge of the consultant’s accounting system or the contract involves procurement of new equipment, the financial review will be made by the public agency in conjunction with the Indiana Department of Transportation’s Accounting and Control Division.

(L) Negotiations for Contract. Upon completion of the assessment of the consultant’s proposal, the public agency will comply as follows:

(1) Negotiations of the contract for the work will take place with the public agency and the group negotiating the contract, with documentation of the use of the evaluations during negotiations and a preliminary agreement developed and submitted from any necessary reviews and approvals. Upon receipt of needed approvals, including local, public agency and Indiana Department of Transportation approvals, a final contract will be executed.

(2) If agreement cannot be reached during negotiations of a contract with reasonable efforts to reach an agreement, either the public agency or consultant may terminate the discussions. In such event, the selection and negotiations with an alternate firm may then be undertaken.

(M) Exceptions to Procedure. In accordance with 23 CFR 172.7(b) and (c), exceptions to the procedures are provided when the project-related expenses do not exceed $25,000, or when specialized qualifications of a single consulting firm are required for the project, or when the project is considered to be an emergency, a particular consultant may be selected with concurrence of the Indiana Department of Transportation. In such cases, the public agency will prepare and submit a preliminary agreement to the Indiana Department of Transportation for review and approval.

(N) Notice to Proceed with Work. When approvals have been received by the Indiana Department of Transportation on the contract along with authorization to proceed, a written notice to proceed with the work will be given to the consultant by the public agency. No compensation will be made for work undertaken prior to such notice to proceed. [Ord. 1145 § 1, 2000; Ord. 1446 § 2, 2010. Code 2000 § 177.08].

3.15.090 Particular procedures involving public works that cost at least $150,000 – Added rules for projects less than or at least $25,000,000.

(A) Whenever the cost of a project will be at least $150,000, the board shall prepare general plans and specifications describing the kind of public work required, but shall avoid specifications which might unduly limit competition. If the project involves the resurfacing (as defined by IC 8-14-2-1) of a road or street, the specifications must show how the weight or volume of the materials will be accurately measured and verified.

(B) The board shall file the plans and specifications in a place reasonably accessible to the public, which shall be specified in the notice required by subsection (C) of this section.

(C) Upon the filing of the plans and specifications, the board shall publish notice in accordance with IC 5-3-1 calling for sealed proposals for the public work needed.

(D) The notice must specify the place where the plans and specifications are on file and the date fixed for receiving bids.

(E) The period of time between the date of the first publication and the date of receiving bids shall be governed by the size of the contemplated project in the discretion of the board, but it may not be more than six weeks if the estimated cost of the public works project is less than $25,000,000; and not more than 10 weeks in the event the estimated cost of the project is at least $25,000,000.

(F) The board shall require the bidder to submit a financial statement, a statement of experience, a proposed plan or plans for performing the public work, and the equipment that the bidder has available for the performance of the public work. The statement shall be submitted on forms prescribed by the state board of accounts.

(G) The board may not require a bidder to submit a bid before the meeting at which bids are to be received. The meeting for receiving bids must be open to the public. All bids received shall be opened publicly and read aloud at the time and place designated and not before. Notwithstanding any other law, bids may be opened after the time designated if both of the following apply:

(1) The board makes a written determination that it is in the best interest of the board to delay the opening;

(2) The day, time, and place of the rescheduled opening are announced at the day, time and place of the originally scheduled opening.

(H) The board shall either: (1) award the contract for public work or improvements to the lowest responsible and responsive bidder; or (2) reject all bids submitted.

(I) If the board awards the contract to a bidder other than the lowest bidder, the board must state in the minutes or memoranda, at the time the award is made, the factors used to determine which bidder is the lowest responsible and responsive bidder and to justify the award. The board shall keep a copy of the minutes or memoranda available for public inspection.

(J) In determining whether a bidder is responsive, the board may consider the following factors:

(1) Whether the bidder has submitted a bid or quote that conforms in all material respects to the specifications.

(2) Whether the bidder has submitted a bid that complies specifically with the invitation to bid and the instructions to bidders.

(3) Whether the bidder has complied with all applicable statutes, ordinances, resolutions, or rules pertaining to the award of a public contract.

(K) In determining whether a bidder is a responsible bidder, the board may consider the following factors:

(1) The ability and capacity of the bidder to perform the work.

(2) The integrity, character, and reputation of the bidder.

(3) The competence and experience of the bidder.

(L) The board shall require the bidder to submit an affidavit: (1) that the bidder has not entered into a combination or agreement: (a) relative to the price to be bid by a person; (b) to prevent a person from bidding; or (c) to induce a person to refrain from bidding; and (2) that the bidder’s bid is made without reference to any other bid. [Ord. 1517 § 2, 2012. Code 2000 § 177.09].

3.15.100 Additional provisions regarding responsible and responsive bidders.

(A) In addition to the provisions of HMC 3.15.090(J) and (K), in order to determine whether a contractor is a “responsible and responsive bidder” for the award of a public works contract, the contractor must submit the following information and supporting documentation verified under oath on a form designated as a “responsible and responsive bidder affidavit of compliance,” in order for the bid to be accepted:

(1) Documents evidencing compliance with all applicable laws and ordinances prerequisite to doing business in Indiana;

(2) A valid federal employer tax identification number or, if an individual, a valid social security number;

(3) A statement of compliance with provisions of Section 2000e of Chapter 21, Title 42 of the United States Code and Federal Executive Order No. 11246 as amended by Executive Order No. 11375 (known as the Equal Opportunity Employer provisions);

(4) Disclosure of the name and address of each subcontractor from whom the contractor has accepted a bid and/or intends to hire on any part of the project. Further, each such subcontractor shall be required to adhere to the requirements set forth herein as though it were bidding directly to the town. Each contractor shall submit all subcontractors’ information and supporting documentation to the town no later than the date and time of the contract award;

(5) Certificates of insurance showing the following coverage necessary for the project:

(a) General liability ($1,000,000 minimum coverage);

(b) Worker’s compensation (statutory limits); and

(c) Automobile liability (minimum of $500,000 per individual, $1,000,000 per occurrence);

(6) The following statement of compliance:

(a) A statement of compliance with all provisions of the Indiana Common Construction Wage law (IC 5-16-7-1 et seq.), and all rules and regulations therein, for the past five years;

(b) Such statement shall also provide that the contractor has reviewed the Common Construction Wage law (or federal Davis-Bacon and related Acts), has reviewed and agrees to pay the applicable common construction wage (or prevailing wage rate) as set forth in the common construction wage rate schedule (or prevailing wage determination) attached to the bid specifications, and will strictly comply with the Common Construction Wage law (or federal Davis-Bacon and related Acts) and related requirements;

(7) Evidence of participation in apprenticeship and training programs applicable to the work to be performed on the project which are approved by and registered with the United States Department of Labor’s Office of Apprenticeship, or its successor organization. The required evidence includes a copy of all applicable apprenticeship standards and apprenticeship agreement(s) for any apprentice(s) who will perform work on the public works project;

(8) A copy of a written plan for employee drug testing;

(9) A statement that individuals who will perform work on the public works project on behalf of the contractor are properly classified as either (a) an employee or (b) an independent contractor under all applicable state and federal laws and local ordinances;

(10) A statement that all employees are (a) covered under a current worker’s compensation insurance policy and (b) properly classified under such policy. If the contractor is insured with a carrier, the evidence of worker’s compensation insurance shall be a copy of the “Information Page” of the contractor’s worker’s compensation policy and any continuation of that information page which includes the name and address of the insured, as well as the class codes the compensation premium is based on and the total estimated remuneration per class code;

(11) A statement listing all employees who will perform work on the public works project and evidence that all listed employees are covered by a health and welfare plan and a retirement plan. The required evidence includes a copy of the summary plan description(s) or similar document(s); and

(12) Documents evidencing any professional or trade license required by law or local ordinance for any trade or specialty area in which the contractor is seeking a contract award. Additionally, the contractor must disclose any suspension or revocation of such license held by the company, or of any director, officer or manager of the company.

(B) Contractors, or first tier subcontractors, submitting bids to the town of Highland, or any of its executive departments or political subdivisions, are required to submit the form designated “Responsible and Responsive Bidder – Affidavit of Compliance” with their bid submission, only once in any calendar year, unless material changes in contractor status occur, as described in subsection (C) of this section. Thereafter, the form will be kept on file in the office of the clerk-treasurer and will remain valid for any subsequent bids made during that calendar year.

(C) Any material change to the contractor’s status, at any time, must be reported in writing to the town within 14 days of its occurrence. Failure to comply with this requirement is grounds for the contractor to be deemed a nonresponsible and nonresponsive bidder.

(D) A contractor who has been found by the Indiana Department of Labor to be in violation of the common construction wage law twice within a three-year period shall be deemed not to be a responsible and responsive bidder for two years from the date of the latest finding.

(E) If all of the above criteria are otherwise satisfied, the town may also consider the following factors, in its discretion, in awarding the project if such information is requested:

(1) Statements as to past performance, which shall give an accurate and complete record of all public works projects completed in the past three years by the contractor. Such statements shall include the names and addresses of the projects, original contract price, final contract price, and the names of all subcontractors used, if applicable, and a statement as to compliance with completion deadlines; and/or

(2) Any determinations by a court or governmental agency for violations of federal, state, or local laws including but not limited to violations of contracting or antitrust laws, tax or licensing laws, environmental laws, the Occupational Safety and Health Act (OSHA), the National Labor Relations Act (NLRA), or federal Davis-Bacon and related Acts. [Ord. 1494 § 1, 2011; Amended during 2012 recodification. Code 2000 § 177.10].

3.15.110 Incomplete submissions by bidders and subcontractors.

It is the sole responsibility of the contractor to comply with all submission requirements at the time it submits its bid to the town. The submission requirements also apply to all subcontractors, except that the contractor shall submit all subcontractor submissions to the town no later than the date and time of the contract award. Contractor and/or subcontractor submissions deemed inadequate or incomplete may result in a determination that the contractor is not a responsible and responsive bidder. [Ord. 1446 § 2, 2010. Code 2000 § 177.11].

3.15.120 Multiple low bids.

When two or more responsible and responsive bidders submit the same low bid, the contract award shall be determined by drawing lots at a public meeting of the town council, unless one bidder is a local contractor and one is a nonlocal contractor, in which event the local contractor shall be awarded the contract. [Ord. 1446 § 2, 2010. Code 2000 § 177.12].

3.15.130 Certified payroll.

All contractors and subcontractors working on a public works project, the value of which meets or exceeds the threshold levels set by the state of Indiana in the Indiana Common Construction Wage Law, shall submit a weekly certified payroll identifying each of its employees by name, the employee’s job classification, hourly rate of pay and hourly fringe benefits rate. Each shall utilize the federal form now known as a WH-347 (or a successor form or a state of Indiana certified payroll form if and when such a form is adopted) which must be submitted on a weekly basis within five days after the end of each week which the contractor or subcontractor performed its work on the public works project. [Ord. 1446 § 2, 2010. Code 2000 § 177.13].

3.15.140 Records and documents submitted to be public records.

All information submitted by a contractor or subcontractor pursuant to this chapter, including certified payrolls, are public records subject to review pursuant to the Indiana Access to Public Records Law (IC 5-14-3-1 et seq.). [Ord. 1446 § 2, 2010. Code 2000 § 177.14].

3.15.150 Materiality.

The requirements of this chapter, set forth in HMC 3.15.100 through 3.15.140, are a material part of the bid documents and the contract and the successful bidder shall insert this chapter in all subcontracts. [Ord. 1446 § 2, 2010. Code 2000 § 177.15].

3.15.160 Bond or certified check – Filing by bidders.

(A) If the cost of the public work is estimated to be more than $200,000, the town and its political subdivisions shall require a bond or a certified check to be filed with each bid by a bidder in the amount determined and specified by the board in the notice of the letting; and

(B) If the cost of the public work is estimated to be not more than $200,000, the town and its political subdivisions may require a bond or a certified check to be filed with each bid by a bidder in the amount determined and specified by the board in the notice of the letting.

(C) The amount of the bond or certified check may not be set at more than 10 percent nor less than six percent of the contract price. The bond or certified check shall be made payable to the town, the department or the political subdivision.

(D) All checks of unsuccessful bidders shall be returned to them by the board upon selection of successful bidders. Checks of successful bidders shall be held until delivery of the performance bond, as provided in IC 36-1-12-14(e). (Confer with IC 36-1-12-4.5) [Ord. 1446 § 2, 2010; Amended during 2012 recodification. Code 2000 § 177.16].

3.15.170 Procedure for accepting quotes.

(A) This section applies whenever a public work project is estimated to cost at least $50,000 and less than $150,000.

(B) The board must proceed under the following provisions:

(1) The board shall invite quotes from at least three persons known to deal in the class of work proposed to be done by mailing them a notice stating that plans and specifications are on file in a specified office. The notice must be mailed not less than seven days before the time fixed for receiving quotes.

(2) The board may not require a person to submit a quote before the meeting at which quotes are to be received. The meeting for receiving quotes must be open to the public. All quotes received shall be opened publicly and read aloud at the time and place designated and not before.

(3) The board shall award the contract for the public work to the lowest responsible and responsive quoter.

(4) The board may reject all quotes submitted. [Ord. 1517 § 3, 2012. Code 2000 § 177.17].

3.15.180 Alternative procedure for projects costing less than $150,000.

For a public work for the routine operation, routine repair, or routine maintenance of existing structures, buildings, or real property in which the cost of the public work is estimated to be less than $150,000, the board may award a contract for that public work in the manner provided in IC 5-22. (Confer with IC 36-1-12-4.9) [Ord. 1446 § 2, 2010. Code 2000 § 177.18].

3.15.190 Alternative procedure for projects costing less than $50,000.

(A) Whenever a public work project is estimated to cost less than $50,000, and a contract is to be awarded, the board may proceed under HMC 3.15.090 or under subsection (B) or (C) of this section.

(B) The board must proceed under the following provisions:

(1) The board shall invite quotes from at least three persons known to deal in the class of work proposed to be done by mailing them a notice stating that plans and specifications are on file in a specified office. The notice must be mailed not less than seven days before the time fixed for receiving quotes.

(2) The board may not require a person to submit a quote before the meeting at which quotes are to be received. The meeting for receiving quotes must be open to the public. All quotes received shall be opened publicly and read aloud at the time and place designated and not before.

(3) The board shall award the contract for the public work to the lowest responsible and responsive quoter.

(4) The board may reject all quotes submitted.

(5) If the board rejects all quotes under subsection (B)(4) of this section, the board may negotiate and enter into agreements for the work in the open market without inviting or receiving quotes if the board establishes in writing the reasons for rejecting the quotes.

(C) The board may not proceed under subsection (B) of this section for the resurfacing (as defined in IC 8-14-2-1) of a road, street, or bridge, unless:

(1) The weight or volume of the materials in the project is capable of accurate measurement and verification; and

(2) The specifications define the geographic points at which the project begins and ends.

(D) For the purposes of this section, if contiguous sections of a road, street, or bridge are to be resurfaced in a calendar year, all of the work shall be considered to comprise a single public work project.

(E) The board may purchase or lease supplies in the manner provided in IC 5-22 and perform the public work by means of its own workforce without awarding a public work contract.

(F) Before the board may perform any work under this section by means of its own workforce, the political subdivision or agency must have a group of employees on its staff who are capable of performing the construction, maintenance, and repair applicable to that work.

(G) Quotes for public works projects costing less than $25,000 may be obtained by soliciting at least three quotes by telephone or facsimile transmission. The seven-day waiting period required by subsection (B)(1) of this section does not apply to quotes solicited under this subsection. (Confer with IC 36-1-12-5) [Ord. 1446 § 2, 2010. Code 2000 § 177.19].

3.15.200 Contracts – Notice to proceed – Failure to award and execute contract and to issue notice – Election by bidder to reject contract.

(A) Except as provided in subsections (B) and (C) of this section, the board shall award the contract and shall provide the successful bidder with written notice to proceed within 60 days after the date on which bids are opened.

(B) If general obligation bonds are to be sold to finance the construction that is the subject of the bid, the board shall allow the bidder 90 days.

(C) If revenue bonds are to be issued, when approved by the utility regulatory commission, or if special taxing district, special benefit, or revenue bonds are to be issued and sold to finance the construction, the board shall allow the bidder 150 days.

(D) A failure to award and execute the contract and to issue notice within the time required by this section entitles the successful bidder to:

(1) Reject the contract and withdraw his bid without prejudice; or

(2) Extend the time to award the contract and provide notice to proceed at an agreed later date.

If the successful bidder elects to reject the contract and withdraw his bid, notice of that election must be given to the board in writing within 15 days of the 60-day expiration date or any other extension date. (Confer with IC 36-1-12-6) [Ord. 1446 § 2, 2010. Code 2000 § 177.20].

3.15.210 Public buildings – Approval of plans and specifications by licensed architect or engineer.

Public work performed or contracted for on a public building, the cost of which is more than $100,000, may be undertaken by the board only in accordance with plans and specifications approved by an architect or engineer licensed under IC 25-4 or 25-31. (Confer with IC 36-1-12-7) [Ord. 1446 § 2, 2010. Code 2000 § 177.21].

3.15.220 Road or street work – Open price provisions – Price adjustments of materials – Limitations.

The board may award a public work contract for road, street, or bridge work subject to the open price provisions of IC 26-1-2-305. The contract may provide that prices for construction materials are subject to price of materials adjustment. When price adjustments are part of the contract, the method of price adjustments shall be specified in the contract. However, this section does not authorize the expenditure of money above the total amount of money appropriated by the town for road, street, or bridge contracts. (Confer with IC 36-1-12-8) [Ord. 1446 § 2, 2010. Code 2000 § 177.22].

3.15.230 Emergencies – Contracts by invitation.

(A) The board, upon a declaration of emergency, may contract for a public work project without advertising for bids if bids or quotes are invited from at least two persons known to deal in the public work required to be done.

(B) The minutes of the board must show the declaration of emergency and the names of the persons invited to bid or provide quotes. (Confer with IC 36-1-12-9) [Ord. 1446 § 2, 2010. Code 2000 § 177.23].

3.15.240 Plans and specifications – Approval by various agencies.

All plans and specifications for public buildings must be approved by the state Department of Health, the division of fire and building safety, and other state agencies designated by statute. (Confer with IC 36-1-12-10) [Ord. 1446 § 2, 2010. Code 2000 § 177.24].

3.15.250 Completion of project – Procedure.

(A) The board must, within 60 days after the completion of the public work project, file in the division of fire and building safety a complete set of final record drawings for the public work project. However, this requirement does not apply to a public work project constructed at a cost less than $100,000. In addition, the filing of the drawings is required only if the project involves a public building.

(B) The division of fire and building safety shall provide a depository for all final record drawings filed, and retain them for inspection and loan under regulated conditions. The fire prevention and building safety commission may designate the Librarian of Indiana as the custodian of the final record drawings. The Librarian shall preserve the final record drawings in the state archives as public documents. (Confer with IC 36-1-12-11) [Ord. 1446 § 2, 2010. Code 2000 § 177.25].

3.15.260 Final payment – Claims by subcontractors, laborers, or suppliers.

(A) When a public work project is to be performed, the board shall withhold final payment to the contractor until the contractor has paid the subcontractors, material suppliers, laborers, or those furnishing services. However, if there is not a sufficient sum owed to the contractor to pay those bills, the sum owed to the contractor shall be prorated in payment of the bills among the parties entitled.

(B) To receive payment, the subcontractor or subcontractors, material suppliers, laborers, or those furnishing services shall file their claims with the board within 60 days after the last labor performed, last material furnished, or last service rendered by them, as provided in HMC 3.15.270 or IC 36-1-12-13.

(C) If there is no dispute between the parties claiming to be entitled to the money withheld, the board shall pay the claim from the money due the contractor and deduct it from the contract price. The board shall take a receipt for payment made on a claim.

(D) If there is a dispute between the parties claiming to be entitled to the money withheld, the board shall retain sufficient money to pay the claims until the dispute is settled and the correct amount is determined. However, the board may make a final and complete settlement with the contractor after 30 days after the date of the completion and acceptance of the public work if the board is furnished with satisfactory evidence indicating the payment in full of all subcontractors, material suppliers, laborers, or those furnishing services.

(E) A claim form must be signed by an individual from the political subdivision or agency who is directly responsible for the project and who can verify:

(1) The quantity of a purchased item; or

(2) The weight or volume of the material applied, in the case of a road, street, or bridge project. (Confer with IC 36-1-12-12) [Ord. 1446 § 2, 2010. Code 2000 § 177.26].

3.15.270 Contract provision for payment of subcontractors, laborers, or suppliers.

A contract for public work must contain a provision for the payment of subcontractors, laborers, material suppliers, and those performing services. The board shall withhold money from the contract price in a sufficient amount to pay the subcontractors, laborers, material suppliers, and those furnishing services. (Confer with IC 36-1-12-13) [Ord. 1446 § 2, 2010. Code 2000 § 177.27].

3.15.280 Contractor’s payment bond for public works projects in excess of $200,000.

(A) The town, department or appropriate political subdivision:

(1) Shall require the contractor to execute a payment bond to the appropriate political subdivision or agency, approved by and for the benefit of the political subdivision or agency, in an amount equal to the contract price if the cost of the public work is estimated to be more than $200,000; and

(2) May require the contractor to execute a payment bond to the appropriate political subdivision or agency, approved by and for the benefit of the political subdivision or agency, in an amount equal to the contract price if the cost of the public work is estimated to be not more than $200,000.

The payment bond is binding on the contractor, the subcontractor, and their successors and assigns for the payment of all indebtedness to a person for labor and service performed, material furnished, or services rendered. The payment bond must state that it is for the benefit of the subcontractors, laborers, material suppliers, and those performing services.

(B) The payment bond shall be deposited with the board. The payment bond must specify that:

(1) A modification, omission, or addition to the terms and conditions of the public work contract, plans, specifications, drawings, or profile;

(2) A defect in the public work contract; or

(3) A defect in the proceedings preliminary to the letting and awarding of the public work contract;

does not discharge the surety. The surety of the payment bond may not be released until one year after the board’s final settlement with the contractor.

(C) A person to whom money is due for labor performed, material furnished, or services provided shall, within 60 days after the completion of the labor or service, or within 60 days after the last item of material has been furnished, file with the board signed duplicate statements of the amount due. The board shall forward to the surety of the payment bond one of the signed duplicate statements. However, failure of the board to forward a signed duplicate statement does not affect the rights of a person to whom money is due. In addition, a failure to forward the statement does not operate as a defense for the surety.

(D) An action may not be brought against the surety until 30 days after the filing of the signed duplicate statements with the board. If the indebtedness is not paid in full at the end of that 30-day period the person may bring an action in court. The court action must be brought within 60 days after the date of the final completion and acceptance of the public work. (Confer with IC 36-1-12-13.1) [Ord. 1446 § 2, 2010. Code 2000 § 177.28].

3.15.290 Contracts in excess of $200,000 – Escrow and retainage – Performance bonds.

The provisions set forth in IC 36-1-12-14 shall apply to public works contracts of the town and its political subdivisions. At the discretion of the contractor, the retainage shall be held by the board or shall be placed in an escrow account with a bank, savings and loan institution, or the state as the escrow agent. The escrow agent shall be selected by mutual agreement between board and contractor or contractor and subcontractor under a written agreement among the bank or savings and loan institution and: (A) the board and the contractor; or (B) the subcontractor and the contractor. The board shall not be required to pay interest on the amounts of retainage that it holds under this section. (Confer with IC 36-1-12-14) [Ord. 1446 § 2, 2010. Code 2000 § 177.29].

3.15.300 Wage scale and antidiscrimination provisions.

(A) A contract by the board for public work must conform to the wage scale provisions of IC 5-16-7.

(B) A contract by the board for public work must conform with the antidiscrimination provisions of IC 5-16-6. The board may consider a violation of IC 5-16-6 a material breach of the contract, as provided in IC 22-9-1-10. (Confer with IC 36-1-12-15) [Ord. 1446 § 2, 2010. Code 2000 § 177.30].

3.15.310 Necessity of compliance with public works law.

A contract for public work by this town or a political subdivision is void if it is not let in accordance with this chapter or IC 36-1-12. (Confer with IC 36-1-12-16) [Ord. 1446 § 2, 2010. Code 2000 § 177.31].

3.15.320 Road or street work contracts – Timely payment of claims – Final payment – Interest for late payment.

(A) A contract for road or street work must contain a provision for the timely payment of claims made by the contractor.

(B) Each contract must provide for final payment within 120 days after final acceptance and completion of the contract. Final payment may not be made on any amount that is in dispute, but final payment may be made on that part of a contract or those amounts that are not in dispute.

(C) For each day after 120 days, the board shall pay to the contractor interest for late payment of money due to the contractor. However, interest may not be paid for those days that the delay in payment is not directly attributable to the board. The annual percentage rate of interest that the board shall pay on the unpaid balance is 12 percent. (Confer with IC 36-1-12-17) [Ord. 1446 § 2, 2010. Code 2000 § 177.32].

3.15.330 Change or alterations of specifications – Change orders.

(A) If, in the course of the construction, reconstruction, or repair of a public work project, it becomes necessary to change or alter the original specifications, a change order may be issued to add, delete, or change an item or items in the original contract. The change order becomes an addendum to the contract and must be approved and signed by the board and the contractor.

(B) If a licensed architect or engineer is assigned to the public work project, the change order must be prepared by that person.

(C) A change order may not be issued before commencement of the actual construction, reconstruction, or repairs except in the case of an emergency. In that case, the board must make a declaration, and the board’s minutes must show the nature of the emergency.

(D) The total of all change orders issued that increase the scope of the project may not exceed 20 percent of the amount of the original contract. A change order issued as a result of circumstances that could not have been reasonably foreseen does not increase the scope of the project.

(E) All change orders must be directly related to the original public work project.

(F) If additional units of materials included in the original contract are needed, the cost of these units in the change order must be the same as those shown in the original contract. (Confer with IC 36-1-12-18) [Ord. 1446 § 2, 2010. Code 2000 § 177.33].

3.15.340 Dividing cost of a single public work project into two or more projects prohibited.

(A) For purposes of this section, the cost of a public work project includes the cost of materials, labor, equipment rental, and all other expenses incidental to the performance of the project.

(B) The cost of a single public work project may not be divided into two or more projects for the purpose of avoiding the requirement to solicit bids.

(C) A bidder or quoter or a person who is a party to a public work contract who knowingly violates this section commits the infraction described in IC 36-1-12-19(c) and may not be a party to or benefit from any contract under this chapter for two years from the date of the conviction.

(D) Any board member or officer of a political subdivision or agency who knowingly violates this section commits the infraction described in IC 36-1-12-19(c). (Confer with IC 36-1-12-19) [Ord. 1446 § 2, 2010. Code 2000 § 177.34].

3.15.350 Trench safety systems.

(A) This section applies to a public works project that may require creation of a trench of at least five feet in depth.

(B) IOSHA regulations 29 C.F.R. 1926, Subpart P, for trench safety systems shall be incorporated into the contract documents for a public works project.

(C) The contract documents for a public works project shall provide that the cost for trench safety systems shall be paid for:

(1) As a separate pay item; or

(2) In the pay item of the principal work with which the safety systems are associated. (Confer with IC 36-1-12-20) [Ord. 1446 § 2, 2010. Code 2000 § 177.35].

3.15.360 Plumbing installations – Proof of licensure.

(A) A person who submits a bid for a public works contract under this chapter that involves the installation of plumbing must submit evidence that the person is a licensed plumbing contractor under IC 25-28.5-1.

(B) If a public works contract under this chapter is awarded to a person who does not meet the requirements of subsection (A) of this section, the contract is void. (Confer with IC 36-1-12-21) [Ord. 1446 § 2, 2010. Code 2000 § 177.36].

3.15.370 Severability.

If any portion of this chapter or the application thereof to any person or circumstance is held invalid, such invalidity shall not affect other portions or applications of this chapter which can be given effect without the invalid portions or applications and, to this end, the portions of this chapter are severable. [Ord. 1446 § 2, 2010. Code 2000 § 177.37].