6.140.030 Fees.

Fees for building activities are set forth pursuant to Table 6.140.030-1:

Table 6.140.030-1 Building Fees 

Section

Activity

Fee

1

 

 

Commercial Permits

 

 

A

 

Commercial plan review

65% of permit fee

 

B

 

Commercial manufactured home placement – Application3

$533

 

C

 

Commercial manufactured home placement – Permit3

$467

 

D

 

Phased plan review approval

$974

 

E

 

Deferred plan review submittals5

$361

 

F

 

Re-roof

$387

 

G

 

Re-siding

$443

 

H

 

Business change only – Certificate of occupancy

$98.50

 

I

 

Business move-in only

$436.50

2

 

 

Commercial Permits – Total Valuation1

 

 

A

 

Issuance of permit

$94

 

B

 

$0 to $5,000

$150

 

C

 

$5,000.01 to $10,000.00

$250

 

D

 

$10,000.01 to $25,000.00

$250.00 for the first $10,000.00 plus $16.67 for each additional $1,000.00, or fraction thereof, to and including $25,000.00

 

E

 

$25,000.01 to $50,000.00

$500.00 for the first $25,000.00 plus $13.00 for each additional $1,000.00, or fraction thereof, to and including $50,000.00

 

F

 

$50,000.01 to $100,000.00

$825.00 for the first $50,000.00 plus $8.00 for each additional $1,000.00, or fraction thereof, to and including $100,000.00

 

G

 

$100,000.01 to $500,000.00

$1,225.00 for the first $100,000.00 plus $6.00 for each additional $1,000.00, or fraction thereof, to and including $500,000.00

 

H

 

$500,000.01 to $1,000,000.00

$3,625.00 for the first $500,000.00 plus $5.00 for each additional $1,000.00, or fraction thereof, to and including $1,000,000.00

 

I

 

$1,000,000.01 to $5,000,000.00

$6,125.00 for the first $1,000,000.00 plus $4.00 for each additional $1,000.00 or fraction thereof

 

J

 

>$5,000,000.00

$22,125.00 for the first $5,000,000.00 plus $2.00 for each additional $1,000.00 or fraction thereof

3

 

 

Residential Permits – Total Valuation1, 9

 

 

A

 

Issuance of permit

$94

 

B

 

$0 to $2,000.00

$75

 

C

 

$2,000.01 to $5,000.00

$100

 

D

 

$5,000.01 to $10,000.00

$250

 

E

 

$10,000.01 to $25,000.00

$250.00 for the first $10,000.00 plus $16.67 for each additional $1,000.00 or fraction thereof to and including $25,000.00

 

F

 

$25,000.01 to $50,000.00

$500.00 for the first $25,000.00 plus $6.00 for each additional $1,000.00 or fraction thereof to and including $50,000.00

 

G

 

$50,000.01 to $200,000.00

$650.00 for the first $50,000.00 plus $3.85 for each additional $1,000.00 or fraction thereof to and including $200,000.00

 

H

 

$200,000.01 to $500,000.00

$1,227.50 for the first $200,000.00 plus $1.30 for each additional $1,000.00 or fraction thereof to and including $500,000.00

 

I

 

$500,000.01 to $1,000,000.00

$1,617.50 for the first $500,000.00 plus $1.20 for each additional $1,000.00 or fraction thereof to and including $1,000,000.00

 

J

 

>$1,000,000.00

$2,217.50 for the first $1,000,000.00 plus $1.10 for each additional $1,000.00 or fraction thereof

 

K

 

COMBO SFR (mech, plb, radon, etc.)

Fee is an additional 40% of base SFR permit fee (the additional 40% is not subject to plan review fees)

 

L

 

Adult family home conversion

Conversion is calculated at 30% of an SFR base rate (includes permit and plan review)

 

M

 

Phased plan review approval

$976.08 per phase

 

N

 

Simple garage, carport, patio cover or deck

$350.50 (includes issuance and state fee)

4

 

 

Other Activities

 

 

A

 

Issuance of permit

$94

 

B

 

Residential plan review

65% of permit fee

 

C

 

Manufactured home placement – Application

$158

 

D

 

Manufactured home placement – Issuance

$361

 

E

 

Lot setback revision

$108

 

F

 

Re-roof (other than commercial)

$220

 

G

 

Re-siding (other than commercial)

$220

 

H

 

Roofing, siding, window contractor combination

$89

 

I

 

Sign permit for one freestanding sign

$250

 

J

 

Sign permit for a single fascia (wall) sign

$150

 

K

 

Sign permit for multiple signs (any combination of freestanding and/or fascia)7

$250

 

L

 

Removal permit for manufactured home

$135

 

M

 

Title elimination for manufactured home

$105

 

N

 

State Building Code issuance fee

$4.50

 

O

 

Approaches, driveways, sidewalks or curbs4

$136

 

P

 

Replacement approaches, driveways, sidewalks or curbs4

$68

 

Q

 

Moved buildings

$539

 

R

 

Demolition

$164

 

S

 

Erosion and stormwater review and inspection

$270

5

 

 

Other Inspections and Activities

 

 

A

 

Inspections outside of normal business hours (minimum charge of 2 hours overtime rate)

$148 per hour (minimum $296.00)

 

B

 

Reinspection fees assessed under provisions of Section 305(g)

$148 per hour

 

C

 

Inspections for which no fee is specially indicated

$148 per hour

 

D

 

Additional plan review required by changes, additions or revisions to plans or research related to structure or occupancy (minimum charge of one-half hour)

$148 per hour

6

 

 

Mechanical Fees

 

 

A

 

Issuance of permit

$94

 

B

 

Issuance of each supplemental permit to an existing permit

$53

 

C

 

Installation or relocation of each forced-air or gravity-type furnace or burner

$29

 

D

 

Installation or relocation of each suspended heater, recessed wall heater or floor-mounted heater

$29

 

E

 

Installation, relocation or replacement of each appliance vent installed and not included in an appliance permit

$29

 

F

 

Repair, alteration, and addition to each heating appliance, refrigeration, cooling, adsorption unit, or each heating, cooling, absorption or evaporative cooling system

$29

 

G

 

Installation or relocation of each boiler or commercial compressor

$89

 

H

 

Each air-handling unit

$29

 

I

 

Each evaporative cooler other than portable type

$29

 

J

 

Each ventilation fan connected to a single duct

$29

 

K

 

Each ventilation system which is not a portion of any heating or air-conditioning system authorized by a permit

$29

 

L

 

Installation of each hood which is served by mechanical exhaust, including the ducts for such hood

$29

 

M

 

Installation or relocation of each domestic-type incinerator

$29

 

N

 

Installation or relocation of each commercial industrial-type incinerator

$89

 

O

 

Each appliance or piece of equipment by this code but not classed in other appliance categories, or for which no other fee is listed in this code

$29

 

P

 

Fuel-gas piping system of 1 to 5 outlets

$89

 

Q

 

Each additional gas-piping system outlet per outlet

$29

 

R

 

Radon6 mitigation system

$89

 

S

 

Woodstoves, inserts, and freestanding stoves

$89

 

T

 

Each water heater and/or vent

$29

 

U

 

Limited trade permit8

$67

7

 

 

Plumbing Fees

 

 

A

 

Issuance of permit

$94

 

B

 

Issuance of each supplemental permit to an existing permit

$53

 

C

I

Plumbing fixtures – Up to 5

$192

 

 

II

Each additional plumbing fixture

$35

 

 

III

Homeowner water heater replacement

$66

 

D

 

Each building sewer connection and each manufactured home park sewer connection

$122

 

E

 

Each private sewage disposal system

$122

 

F

 

Each industrial waste pretreatment interceptor including its trap and vent, excepting kitchen-type grease interceptors functioning as fixture traps

$122

 

G

 

Each installation, alteration or repair of water piping and/or water treating equipment

$122

 

H

 

Each repair or alteration of drainage or vent piping, each fixture

$122

 

I

 

Each lawn sprinkler system on any one meter including backflow protection devices

$122

 

J

 

Atmospheric-type vacuum breakers not included in item L: 1 to 5

$178

 

K

 

Atmospheric-type vacuum breakers not included in item L: Over 5, each

$35

 

L

 

Each backflow protective device other than atmospheric-type vacuum breakers: 2-inch diameter and smaller

$122

 

M

 

Each backflow protective device other than atmospheric-type vacuum breakers: Over 2-inch diameter

$122

 

N

 

Limited trade permit8

$67

Notes

1    Valuation shall be determined by the building official pursuant to Section 6.140.020(2).

2    Reserved for future use.

3    Permits for any modular requiring construction at the site shall be assessed based on value as set forth in Section 2 of this table.

4    Fees shown for sidewalks, curbs and driveway approaches are for separate permits. If any combination of these is installed in one (1) operation, only one (1) permit is required.

5    Items requiring separate permits, such as fire sprinkler systems, are not charged additionally. The value of the items must be in the building valuation and then a separate permit and plan review fee is assessed. This separate permit fee constitutes the deferred fee for such items.

6    All new single-family homes and residential additions require radon inspections.

7    Applied for, issued, installed and inspected for one (1) tenant under one (1) permit, with a maximum of three (3) inspections.

8    Limited trade permits are only available for push/pull or removal/replacement of a furnace, air conditioner, water heater, or heat pump.

(Sec. 30 of Ord. 1997-12-46; amended by Sec. 1 (Exh. A) of Ord. 2001-12-11; amended by Sec. 1 (Exh. A) of Ord. 2002-11-07; amended by Sec. 1 (Exh. A) of Ord. 2002-02-09; amended by Ord. 2004-12-02; amended by Ord. 2005-12-01; amended by Sec. 1 (Exh. A) of Ord. 2006-05-01; amended by Sec. 1 of Ord. 2007-04-17; amended by Sec. 1 of Ord. 2008-02-01; amended by Sec. 1 of Ord. 2008-07-05; amended by Sec. 1 (Exh. A) of Ord. 2009-06-08; amended by Sec. 6 (Exh. F) of Ord. 2011-07-03; amended by Sec. 1 (Exh. 3) of Ord. 2012-02-03; amended by Sec. 1 of Ord. 2012-07-03; amended by Sec. 1 (Exh. A) of Ord. 2012-09-14; amended by Sec. 1 of Ord. 2013-06-03; amended by Sec. 5 of Ord. 2016-09-03; amended by Sec. 2 of Ord. 2018-10-02)