Chapter 12.20
PUBLIC WORKS IMPROVEMENT REVIEW AND INSPECTION FEES
Sections:
12.20.010 Review and inspection fee for public work improvements.
12.20.030 Public works improvement bid item prices.
12.20.010 Review and inspection fee for public work improvements.
The review and inspection fee shall be based on the construction cost estimate obtained from the Public Works Improvement Bid Item Prices sheet provided in YMC 12.20.030. For items that are not included in YMC 12.20.030, the consulting engineer shall provide the per unit cost to be reviewed and approved by the city engineer. The review and inspection fees shall be set forth in the city of Yakima master fee schedule adopted via resolution by the city council. (Ord. 2022-040 § 68, 2022; Ord. 2012-59 § 1, 2012: Ord. 2011-19 § 1 (part), 2011).
12.20.020 Payment.
Payment of the review and inspection fees shall be as follows:
• Two hundred fifty dollars shall be paid at the time plans are submitted to the city engineer and shall be a nonrefundable charge.
• Remainder of fee balance, if any, shall be paid following review and prior to approved plans being released to the consulting engineer/owner/developer. (Ord. 2012-59 § 2, 2012: Ord. 2011-19 § 1 (part), 2011).
12.20.030 Public works improvement bid item prices.
ITEM DESCRIPTION |
UNIT |
QUANTITY |
UNIT PRICE |
AMOUNT |
---|---|---|---|---|
Clearing and Grading |
|
|||
Half Street Improvement |
LF |
|
$6.00 |
|
Full Street Improvement |
LF |
|
$12.00 |
|
OTHER |
|
|
|
|
Clearing and Grading Total: |
|
|||
Street |
|
|||
Saw Cut (per inch depth) |
LF |
|
$1.00 |
|
Crushed Surfacing Top Course |
TON |
|
$15.00 |
|
Crushed Surfacing Base Course |
TON |
|
$14.00 |
|
Asphalt Treated Base |
TON |
|
$60.00 |
|
Hot Mix Asphalt |
TON |
|
$70.00 |
|
Pavement Repair |
SY |
|
$40.00 |
|
Porous Asphalt Pavement |
SF |
|
$4.00 |
|
Porous Concrete Pavement |
SF |
|
$5.00 |
|
Cement Concrete Traffic Curb and Gutter |
LF |
|
$9.00 |
|
Cement Concrete Sidewalk, 4-Inch Depth |
SY |
|
$27.00 |
|
Cement Concrete Sidewalk, 6-Inch Depth |
SY |
|
$30.00 |
|
Handicap Ramp (Separate of Commercial Approach) |
EA |
|
$750.00 |
|
Commercial Approach |
EA |
|
$3,500.00 |
|
OTHER |
|
|
|
|
Street Total: |
|
|||
Storm Drainage System |
|
|||
8-Inch Pipe |
LF |
|
$22.00 |
|
10-Inch Pipe |
LF |
|
$25.00 |
|
12-Inch Pipe |
LF |
|
$30.00 |
|
18-Inch Pipe |
LF |
|
$35.00 |
|
24-Inch Pipe |
LF |
|
$40.00 |
|
Type 1 Catch Basin |
EA |
|
$750.00 |
|
Type 1L Catch Basin |
EA |
|
$1,000.00 |
|
Curb Inlet |
EA |
|
$650.00 |
|
Connection to Existing Catch Basin/Manhole |
EA |
|
$1,600.00 |
|
Retention System |
LF |
|
$70.00 |
|
Infiltration Swale |
LF |
|
$6.00 |
|
Pollution Control |
EA |
|
$200.00 |
|
OTHER |
|
|
|
|
Storm Drainage Total: |
|
|||
Sanitary Sewer System |
|
|||
8-Inch Pipe |
LF |
|
$30.00 |
|
10-Inch Pipe |
LF |
|
$35.00 |
|
12-Inch Pipe |
LF |
|
$40.00 |
|
48-Inch Manhole |
EA |
|
$1,700.00 |
|
72-Inch Manhole |
EA |
|
$3,000.00 |
|
Extra Depth Excavation (per foot depth over 12' deep) |
LF |
|
$2.00 |
|
Extra Depth Manhole (per foot over 12' depth) |
FT |
|
$110.00 |
|
OTHER |
|
|
|
|
Sanitary Sewer System Total: |
|
|||
Water System |
|
|||
4-Inch Pipe |
LF |
|
$15.00 |
|
6-Inch Pipe |
LF |
|
$20.00 |
|
8-Inch Pipe |
LF |
|
$25.00 |
|
10-Inch Pipe |
LF |
|
$30.00 |
|
12-Inch Pipe |
LF |
|
$40.00 |
|
4-Inch Gate Valve |
EA |
|
$550.00 |
|
6-Inch Gate Valve |
EA |
|
$725.00 |
|
8-Inch Gate Valve |
EA |
|
$1,000.00 |
|
10-Inch Gate Valve |
EA |
|
$1,250.00 |
|
12-Inch Gate Valve |
EA |
|
$1,500.00 |
|
Fire Hydrant Assembly |
EA |
|
$1,800.00 |
|
Blow Off Assembly |
EA |
|
$850.00 |
|
Air and Vacuum Assembly |
EA |
|
$1,000.00 |
|
Water Valve Box |
EA |
|
$65.00 |
|
OTHER |
|
|
|
|
Water System Total: |
|
|||
Street Lighting |
|
|||
Aluminum Street Light |
EA |
|
$3,000.00 |
|
Service Meter |
EA |
|
$300.00 |
|
Electrical Junction Box |
EA |
|
$150.00 |
|
Electrical Conduit |
LF |
|
$3.00 |
|
OTHER |
|
|
|
|
Street Lighting Total: |
|
|||
Miscellaneous |
|
|||
Monument |
EA |
|
$300.00 |
|
Street Sign |
EA |
|
$200.00 |
|
Pavement Marking |
LF |
|
$1.00 |
|
Control Density Fill |
CY |
|
$80.00 |
|
Adjust Existing Utilities |
EA |
|
$220.00 |
|
Sod Installation |
SY |
|
$17.00 |
|
OTHER |
|
|
|
|
Miscellaneous Total: |
|
|||
Project Total: |
|
LEGEND
LF = Linear Foot
SY = Square Yard
SF = Square Foot
EA = Each
FT = Foot
CY = Cubic Yard
(Ord. 2011-19 § 1 (part), 2011).