13.40.010 Purpose.

The purpose of this chapter is to provide for city water rights to support new development. This purpose shall be achieved through the transfer of water rights to the city or the payment of fees to the city to be used to acquire additional water rights as a condition of connection to the city’s municipal water system. The purpose for requiring a transfer of water rights or payment in lieu thereof is to enhance the public health, safety, and welfare through a provision designed to enable the city to meet the future water service needs of property subject to this chapter and in the city urban growth area in general. (Ord. 07-003 § 1).

13.40.020 Types of water rights.

This chapter shall apply to all of the various types of water rights or rights to water that are appurtenant to or associated with the real property that is subject to this chapter (excluding waters in an irrigation district formed pursuant to Chapter 87.03 RCW), and may include as necessary, at the election of the city, any associated real and personal property interests in and to the water rights at issue. For example, the various types of water rights subject to this chapter include, but are not necessarily limited to, the following: permits, certificates, and claims issued by or on file with the Washington State Department of Ecology, or any of its predecessors. (Ord. 07-003 § 1).

13.40.030 Annexations.

Annexations are not subject to this chapter. (Ord. 07-003 § 1)

13.40.040 Short plats, subdivisions, binding site plans, planned developments and other permits.

(1) Upon application for a short plat, subdivision, binding site plan, or planned development, the owner of the property that is the subject of the application shall transfer water rights associated with the property to the city, subject to the provisions in KMC 13.40.050. Alternatively, at the election of the city, the owner and city may enter into an agreement to transfer the water rights to the city at a later time. The purpose of this deferment provision is to accommodate (a) potential delays encountered in the process to transfer the water rights to the city, or (b) the continued use of the water rights associated with uses in existence at the time of the application and anticipated to continue until further development of the property that is the subject of the application. As part of the agreement, the city may require (a) the property owners to acquire adequate water rights and transfer the same to the city, and/or (b) the property owners to deposit an amount into the city water fund equal to the payment in lieu of transfer provided in KMC 13.40.050, which sum is refundable to the extent of the successful transfer of the water rights.

(2) Upon application for a building permit (except for a single-family residence or other structures which will not require water service greater than that of a single-family residence) on an existing lot of record, the owner of the property shall transfer water rights consistent with subsection (1) of this section, or, alternatively, the city may forego the water right transfer and require a payment in lieu of the water right as set forth in KMC 13.40.050.

(3) As part of the determination made pursuant to this section, the city may take into consideration and provide appropriate credit for property that previously complied with the provisions of this chapter. (Ord. 07-003 § 1).

13.40.050 Amount of water and payment in lieu.

(1) Water Use Determination. The amount of water rights to be transferred to the city pursuant to KMC 13.40.040 shall be sufficient to serve the estimated equivalent residential units (ERUs) of anticipated water usage for the area that is the subject of application based upon the city’s regulations applicable to development of the property in effect at the time of application for the short plat, subdivision, binding site plan, planned development, or building permit as submitted. This determination shall be made by the city engineer and the determination communicated in writing to the applicant property owner(s) within 20 days of the city’s receipt of the KMC 13.40.040 application for approval. In the calculation of the amount of water rights that must be transferred to the city, credit may be provided for any existing and previously approved connections to the city’s municipal water system that are currently in use on the subject property. In addition, if the owners of property subject to the application of the provisions of this chapter have an exempt well or wells and desire to transfer the water rights associated with said wells, as currently provided for in RCW 90.44.105, then credit shall also be provided for the water use associated with said wells to the extent the water rights associated with said wells are successfully transferred to the city.

(2) Excess Water Rights. To the extent the water rights associated with the subject property exceed the anticipated water usage for the subject property as determined pursuant to subsection (1) of this section, the city in its sole discretion may (a) require the owner(s) of the subject property to transfer any amount of the excess water rights to the city and the city shall pay the owner(s) of the excess water rights for the excess water rights to be transferred to the city an amount representing the then current market value of the excess ERUs as determined by the city fee schedule, or (b) allow said owner to transfer the excess water rights to the city in exchange for credits to be applied to other property owned by said owner within the city limits of the city, subject to the provisions of KMC 13.40.040. In the event the city acquires the excess water rights, the transfer will be processed simultaneously with and as part of the transfer process outlined in KMC 13.40.080, and the city shall be responsible for the proportionate share of the transfer costs attributable to the excess water rights.

(3) Payment in Lieu. In the event (a) no water rights are associated with the property that is the subject of the KMC 13.40.040(1) application, (b) the water rights associated with said property are less than the city engineer determines to be sufficient to serve the estimated ERUs of anticipated water usage for the area that is the subject of application as determined by the city engineer pursuant to subsection (1) of this section, (c) the water rights successfully transferred to the city are less than the city engineer determines to be sufficient to serve the estimated ERUs of anticipated water usage for the area that is the subject of application as determined by the city engineer pursuant to subsection (1) of this section, or (d) a building permit application is sought and the city does not require water rights to be transferred as set forth in KMC 13.40.040(2), then the city may elect to have the owner(s) of the subject property pay to the city, at the then current market value as determined by the city fee schedule, such sum that represents the current market value of the water rights the city estimates will be necessary to serve the property as determined in subsection (1) of this section.

(4) Payment of Costs. The owner(s) of property subject to the application of the provisions of this chapter shall pay the city for all costs associated with (a) the city’s determination of the anticipated water usage for the subject property and current market value of an ERU of water and all costs associated with the transfer of water rights to the city and (b) the costs associated with completing the transfer and acquisition of the water rights. The owner(s) of property required to make payment to the city in lieu of transfer of water rights to the city shall also pay the city’s estimated costs of processing the transfer and acquisition of the water rights. The term “costs” as used in this subsection shall include, but is not limited to, city staff time, engineering fees, attorney fees, planning fees, application fees, Kittitas County Water Conservancy Board Fees, publication fees, and any other fees or charges associated with processing and recording the transfer and acquisition of water rights.

(5) Appeal. Any decision committed to the city engineer will be reviewed by the city mayor, provided the affected property owner serves a written notice to the city requesting the review within 14 calendar days of the issuance of the written recommendation of the city engineer. If a written notice requesting review is not timely served upon the city, then the city engineer’s recommendation shall be the final decision of the city. If a written notice requesting review is timely served on the city, the city administrator shall review the recommendation of the city engineer and issue a final decision within 20 calendar days of the service of the notice requesting review on the city. Any final decision may be appealed to superior court within the applicable time frame(s) pursuant to state law. (Ord. 07-008 § 1; Ord. 07-003 § 1).

13.40.060 Payments made by the city.

All money paid by the city to owners pursuant to the application of this chapter shall be paid by the city water fund. Those water rights purchased pursuant to this chapter shall become assets of the city domestic water utility and part of the city’s water system. (Ord. 07-003 § 1).

13.40.070 Payments received by the city.

All money paid to the city pursuant to this chapter shall be paid to the city water fund. All money paid to the city pursuant to this chapter shall be used by the city water utility for the purchase of water rights and to process applications for new water rights for the city to be added to the city domestic water utility system. Alternatively, to the extent permitted by the laws of the state of Washington, the city may use the money deposited into the city water fund pursuant to this chapter to finance water conservation measures that have the same effect of expanding the city’s municipal water system capacity. (Ord. 07-003 § 1).

13.40.080 Form of transfer and conveyance of water right.

The transfer of water rights pursuant to this chapter shall be in such forms as may be approved by the city. Owners of property transferring water rights pursuant to this chapter shall execute all documents required by the city and/or any other governmental entity that may be necessary to achieve the purposes of this chapter. Those documents may include, but are not limited to, change in point of diversion, change in place of use, change in purpose of use, and any other documents or forms. In order for a water right transfer to be completed, the water right transfer must (a) ultimately be approved by the Department of Ecology and all appeal periods must have expired without challenge, and (b) be changed to a municipal water right. The owner(s) of the property transferring water rights pursuant to this chapter must convey the water right to the city by statutory warranty deed or other appropriate conveyance instrument, as determined by the city, upon completion of the water right transfer; provided, however, that the actual conveyance may be delayed to coincide with the city’s approval of the application described in this chapter, or as otherwise set forth in an agreement between the property owner(s) and the city. (Ord. 07-003 § 1)